ALLIANCE LANDFILL
TAYLOR, PA

CHALLENGE
Waste Management required a retaining wall solution for an access road to support the
construction of a landfill pad at one of their sanitary solid waste landfill sites.


SOLUTION
Pinnacle Design/Build constructed an MSE Berm retaining wall to support the construction of
the access road and to provide a vertical expansion for the landfill waste pad.


VALUE
Pinnacle Design/Build had the necessary knowledge and expertise to construct the MSE Berm
retaining wall for this landfill project.

PROJECT FACTS

Wall Area: 62,985 SF
Max Height: 61 FT
Completed 2021

MSE BERM